RRP (resource requitment planning)
A B
C(3) D(1) C(3) E(2)
item | nomor operasi | work center | operasi | set'up (jam) | waktu operasi (jam) |
A | 10 | 1030 | assembly | 0 | 3 |
B | 10 | 1030 | assembly | 0 | 4 |
C | 10 | 1012 | milling | 0,6 | 0,6 |
20 | 1020 | drilling | 2,7 | 0,7 | |
30 | 1012 | milling | 2,9 | 0,4 | |
40 | 1018 | grinding | 3 | 0,6 | |
D | 10 | 1012 | milling | 0,5 | 0,5 |
20 | 1020 | drilling | 3,2 | 0,3 | |
30 | 1018 | grinding | 2,3 | 0,2 | |
E | 10 | 1012 | milling | 0,6 | 0,2 |
20 | 1020 | drilling | 2,5 | 0,5 | |
30 | 1012 | milling | 2,8 | 0,6 | |
40 | 1018 | grinding | 1,6 | 0,4 |
Dengan EOQ:
A = 15
B = 10
C = 20
D = 30
E = 35
WSO= untuk C (milling) = (0,6+2,9)/20+(0,6+0,4) = 1,175 jam
(drilling) = (2,7/20)+(0,7) = 0,835 jam
(grinding) = (3,0/20)+(0,6) = 0,75 jam
WSO= untuk D (milling) = (0,5/30)+(0,5) = 0,516 jam
(drilling) = (3,2/30)+(0,3) = 0,407 jam
(grinding) = (2,3/30)+(0,2) = 0,277 jam
WSO= untuk E (milling) = (0,6+2,8)/35+(0,2+0,6) = 0,897 jam
(drilling) = (2,5/35)+(0,5) = 0,57 jam
(grinding) = (1,6/35)+(0,4) = 0,45 jam
WSO =untuk A(assembly) = (0/15)+(3,0) = 3 jam
WSO =untuk B(assembly) = (0/10)+(4,0) = 4 jam
item | work center | waktu standar operasi per unit |
C (Q= 20) | milling | 1,175 |
drilling | 0,835 | |
grinding | 0,75 | |
D (Q = 30) | milling | 0,516 |
drilling | 0,407 | |
grinding | 0,277 | |
E (Q = 35) | milling | 0,897 |
drilling | 0,57 | |
grinding | 0,45 | |
A (Q = 15) | assembly | 3 |
B (Q = 35) | assembly | 4 |
Bill of resource:
A (C & D) = milling = 1,175 (3)+ 0,516 = 4,041
Drilling = 0,835 (3) + 0,407 = 2,912
Grinding = 0,75 (3) + 0,277 = 2,527
B (C & E) = milling = 1,175 (3) + 0,897 (2) = 5,319
Drilling = 0,835 (3)+ 0,57 (2)= 3,645
Grinding = 0,75 (3) + 0,45 (2) = 3,15
work center | waktu standar operasi per unit | ||
grup produk A | grup produk B | ||
1012 milling | 4,041 | 5,319 | |
1020 drilling | 2,912 | 3,645 | |
1018 grinding | 2,527 | 3,15 | |
1030 assembly | 3,00 | 4,00 |
Bulan | januari | februari | Maret |
Produk A | 1000 | 1200 | 2500 |
Produk B | 1250 | 750 | 1100 |
Januari
Kebutuhan kapasitas work center milling = 1000 x 4,041+ 1250 x 5,319 = 10689,75
Drilling = 1000 x 2,912+ 1250 x 3,645 = 7468,25
Grinding = 1000 x 2,527+ 1250 x 3,15 = 6464,5
Assembly = 1000 x 3,00 + 1250 x 4,00 = 8000
Februari
Kebutuhan kapasitas work center milling = 1200 x 4,041+ 750 x 5,319 = 8838,45
Drilling = 1200 x 2,912+ 750 x 3,645 = 6228,15
Grinding = 1200 x 2,527+ 750 x 3,15 = 5394,9
Assembly = 1200 x 3,00 + 750 x 4,00 = 6600
Maret
Kebutuhan kapasitas work center milling = 2500 x 4,041+ 1100 x 5,319 = 15953,4
Drilling = 2500 x 2,912+ 1100 x 3,645 = 11289,5
Grinding = 2500 x 2,527+ 1100 x 3,15 = 9782,5
Assembly = 2500 x 3,00 + 1100 x 4,00 = 11900